Question 
The CPM diagram below means that:
A. Activity B has float of 2 and activity E has a late start of 12
B. Activity E has float of 2 and activity C has a late start of 7
C. Activity C has float of 2 and activity E has a late start of 13
D. Activity E has float of 2 and activity C has a late start of 8